The Contractor Owner's Report Pack: WIP, Cash, Profitability, Buyout and More

The report catalog from the Cattlemen OS proof of concept, built for Cattlemen Construction Services in Fort Worth, Texas, and shown on sample data. Eight reports, each answering one question: the WIP schedule (cost-to-cost percent complete, earned revenue, over and under billing), cash position with a 13-week forecast, job cost by cost code, profitability and portfolio with margin fade and months of backlog, commitments and buyout variance, vendor spend with uncoded spend aging, card spend coding, and an exceptions list. For each: the formula, which numbers come from Procore, QuickBooks Online and Ramp, how to read it with real sample figures, and the red flag to watch, plus a fifteen-minute Monday reading order.

By Charley Forey, founder of Build Flows

Key takeaways

  • Each owner report should answer one question: billed ahead or behind, will cash hold, where is each job against budget, who makes money, what is bought out, what is uncoded, who still has to code, and what needs a person today.
  • The WIP schedule uses cost-to-cost: percent complete is cost to date divided by EAC, earned is percent complete times revised contract, and billed minus earned gives over billing (a liability) or under billing (an asset).
  • The 13-week cash forecast starts at today's bank balance, moves AR to the due date plus each client's average days late, and should be read for its low point rather than its ending balance.
  • Buyout variance is budget minus committed on bought-out subcontract codes; a healthy net number can hide a single large overrun.
  • Card spend that reached QuickBooks but has no Procore cost code is a liability hole; age it and chase anything older than seven days.
  • QuickBooks is the system of record for cost and cash, Procore for contract, budget and commitments; a gap between them is a finding in its own right.
  • A fifteen-minute Monday read works in this order: exceptions, card coding, WIP, cash, profitability, commitments, then job cost for flagged jobs.

40 seconds · From a Build Flows walkthrough

WIP and cash reports from Procore and QuickBooks

Live WIP for every job: earned to date, revised contract and backlog, then cash position, open AR, invoices, job cost and cost to complete.

Read the clip transcript

went through the alerts and then now we're diving into the reports so with these reports we're essentially showing the WIP as it's continually happening for the entire project for Procore and QuickBooks and it's resolving in real time for what's earned today what's revised in backlog we have our cash position here for any open balances and any Ar that's outstanding and our invoice is here and then our job costs that we would be provisioning and our cost to complete for what needs to happen and what are uh portfolio margins trend margin trend is for that

Captions adapted from the source video; proper names may reflect automatic transcription. Original segment: 21:54–22:34. Watch at the source.

56 seconds · From a Build Flows walkthrough

Profitability, EAC and the commitment log

Projected gross margin per job, earned vs billed, backlog, EAC and margin percent, then contracts and every commitment with what has been approved.

Read the clip transcript

needs to happen and what are uh portfolio margins trend margin trend is for that so essentially then we'll go through the profitability here the profitability shows our projected gross margin for the each project and our gross profit margin what we've earned versus build any backlog and monthly backlog for each and then revenue and our charts and graphs for projected by project and we can then also see my client here as well and we can see total contract uh what the EAC and projected margin and percent margin is and what we've earned and build to date and any backlog we have our contracts here that are specified for all of our projects and everything that's assigned for our materials and what we have in our commitment log as well and what they've been approved for we can drill into each commitment we can see everything about it if necessary for that project project we

Captions adapted from the source video; proper names may reflect automatic transcription. Original segment: 22:34–23:29. Watch at the source.

An owner of a growing general contractor usually has the numbers. They're spread across Procore, QuickBooks Online and a card platform like Ramp, and each system answers a different part of the question. This guide is the report catalog from the operating system we built for Cattlemen Construction Services in Fort Worth, Texas: eight reports, the one question each answers, where the numbers come from, how to read them, and the red flag worth watching on each.

Every figure below comes from the proof of concept running on sample data, so the job names and dollars are made up. The formulas, sources and warning signs are the real ones. If you want to see the screens move, watch the walkthrough; the reports section starts at about 21:54.

Eight report cards in two rows. WIP schedule asks whether we are billed ahead of or behind the work and shows $210K under. Cash and 13-week forecast asks whether cash holds up and shows a low point of $727K. Job cost asks where each job is against budget. Profitability asks which jobs, clients and PMs make money and shows 13.2% margin. Commitments asks whether every budget line is bought out and shows 86.4%. Vendor spend shows $14K uncoded. Card coding shows 17 charges to code. Exceptions shows 12 open items. Source chips mark Procore, QuickBooks, Ramp and app data on each card.Eight reports, one question each (sample data)

The short version

ReportThe question it answersMain sources
WIP scheduleAre we billed ahead of or behind the work on each job?Procore contract and budget, QuickBooks cost and billing
Cash position and 13-week forecastWill cash hold up for the next 13 weeks?QuickBooks bank, AR, AP; Procore commitments
Job costWhere is each job against budget, by cost code?Procore budget and commitments, QuickBooks actuals, Ramp card spend
Profitability and portfolioWhich jobs, clients and PMs make money, and which don't?Procore contract, PM forecast, QuickBooks cost and revenue
Commitments and buyoutIs every budget line bought out, and is anything over-committed?Procore budget and commitments
Vendor spend and uncoded agingWho do we pay, how much, and what is still uncoded?Ramp, Procore commitment billings, QuickBooks AP
Card spend codingWho still has card charges to code, and how fast do they reach Procore?Ramp transactions, coding in the app
ExceptionsWhat needs a person today?All of the above

Each report has a Download CSV, a Print and an Email me button. That matters more than it sounds. A report the controller can drop into the board pack without retyping it gets used. One that lives only on a screen gets screenshotted and goes stale.

A cropped screenshot of the Reports page in the Cattlemen OS proof of concept on sample data. Tabs across the top read WIP, Cash, Job cost, Profitability, Contracts, Vendor spend and Card spend. Under Card spend, sub-tabs read Coding, QuickBooks vs Procore and Exceptions. The question line reads: who still has Ramp charges to code, and how fast do they reach Procore? Below, tiles show 17 transactions to code, 19 synced to Procore and $14K not in Procore across 24 items on 6 projects.The Reports page: pick the question, get the report (sample data)

Where the numbers come from

Before the reports themselves, it helps to know which system owns which number. When a figure looks wrong, the source tells you who to ask.

A source map. Procore (contract, change orders, budget, commitments, cost codes, refreshed nightly), QuickBooks Online (job cost posted, invoices and AR, bills and AP, bank, refreshed every 15 minutes plus nightly), Ramp (card transactions, cardholders and GL category, every 15 minutes plus nightly) and app data (cost coding, approvals, PM forecasts, instant) connect by dashed lines to eight reports. WIP and profitability read Procore and QuickBooks. Cash reads QuickBooks and Procore. Job cost reads all three. Commitments reads Procore. Vendor spend reads Ramp, Procore and QuickBooks. Card coding reads Ramp and app data. Exceptions reads everything.Which system feeds which report

SourceWhat we readHow often
ProcorePrime contract, approved change orders, budget by cost code, commitments (subcontracts and POs), commitment billingsNightly, plus "Sync now"
QuickBooks OnlineJob cost posted, invoices and AR, bills and AP, bank balancesEvery 15 minutes and nightly
RampCard transactions, cardholders, GL categoryEvery 15 minutes and nightly
The app itselfCost code picks, approvals, PM cost-to-complete forecasts, settingsInstantly

Two rules keep this honest. QuickBooks is the system of record for cost and cash. Procore is the system of record for contract, budget and commitments. When the two disagree on job cost, that gap is a finding in its own right; it isn't something to average away. In Cattlemen's case most of that gap was card spend that reached QuickBooks on category lines and never reached Procore, which is the story in why Ramp bills show $0 in Procore.

1. WIP schedule

The question: are we billed ahead of or behind the work on each job?

How it's built: The WIP uses the cost-to-cost method:

ColumnFormulaSource
Revised contractOriginal contract + approved change ordersProcore
Estimate at completion (EAC)Revised budget, or the PM's cost-to-complete forecast once submittedProcore, app
Cost to dateJob cost postedQuickBooks
% completeCost to date ÷ EACCalculated
Earned revenue% complete × revised contractCalculated
Billed to dateInvoiced to the ownerQuickBooks, Procore prime contract
Over billingBilled − earned, when positive (a liability)Calculated
Under billingEarned − billed, when positive (an asset)Calculated
Projected margin %(Contract − EAC) ÷ contractCalculated
BacklogContract − earnedCalculated

Here's one row worked through so the arithmetic isn't a black box:

A worked WIP row for sample job 26-004 Sample Medical Office TI. Revised contract $1,280,000 from Procore, EAC $1,102,000 from the PM forecast, cost to date $611,600 from QuickBooks, billed to date $640,400. Percent complete is $611,600 divided by $1,102,000, 55.5%. Earned revenue is 55.5% of $1,280,000, $710,400. Billed minus earned is minus $70,000, so the job is $70K underbilled. Projected margin is $178,000 on $1,280,000, 13.9%. A red note says a stale EAC moves every number to its right.One WIP row, worked through (sample data)

How to read it: Start with the billing position tile, then the chart of jobs left and right of zero. In the sample data the company is $210K underbilled in net terms: $262K overbilled on some jobs and $473K underbilled on others, across $7.90M earned and $7.69M billed. The net hides the story. One job alone carries $428K of work done and not billed, and the page says so in a "next step" line pointing at the next pay app.

A cropped screenshot of the work-in-progress schedule in the proof of concept, sample data. The question line reads: are we billed ahead of or behind the work on each job? Tiles show billing position $210K under ($262K overbilled, $473K underbilled), earned to date $7.90M with $7.69M billed, revised contract $13.8M across 6 jobs with $6.90M cost, and backlog $5.88M at a 13.1% projected margin. A next step line flags a job with $428K of work done that hasn't been billed.WIP schedule with the next step spelled out (sample data)

Red flag: a job overbilled by more than 10% of contract (the Exceptions report flags these automatically), or a large underbilling on a job with no pay app coming. Overbilling looks like good cash until the work catches up and the billing doesn't. Underbilling is money you've already spent and haven't asked for.

The deeper treatment of the WIP, including common mistakes like recalculating history and blank-versus-zero, is in construction WIP reporting in Power BI and over/under billing explained. The EAC that drives all of this gets refreshed in the month-end cost-to-complete review.

2. Cash position and 13-week forecast

The question: will cash hold up for the next 13 weeks?

How it's built: The forecast starts at today's bank balance from QuickBooks and walks forward week by week:

  • Inflows: open AR on the date we expect to be paid, which is the due date plus that client's average days late, plus scheduled billings.
  • Outflows: open AP by due date, a payroll and overhead run rate, and committed subcontractor payments from Procore.
  • AR aging: current, 1–30, 31–60, 61–90 and 90+ days, with the invoice list behind each bucket.

The assumptions sit on the page, next to the chart. That is deliberate. A forecast nobody can question is a forecast nobody trusts.

How to read it: Look for the low point, not the ending balance. In the sample data the bank shows $2.71M today, and the projected balance bottoms out at $727K in the week of Feb 8, $1.99M below today. Open AR is $1.15M, and $290K of it is more than 60 days late. The next-step line names the single biggest late invoice ($170K, 101 days past due) and links to a what-if: "test a late payer."

A cropped screenshot of the cash forecast report on sample data. A next step line reads: $290K is more than 60 days late; start with one $170K invoice 101 days past due; cash falls to $727K by Feb 8; test a late payer. Below, a chart titled "Will cash hold up for 13 weeks?" shows weekly cash in as green bars, cash out as orange bars and the projected balance as a falling yellow line, with a What if button. A donut titled "How late are clients paying?" shows $1.15M open AR by days past due.Look for the low point, then test a late payer (sample data)

Red flag: the projected low point dips under a floor you set in advance, for example two payrolls plus the next big sub payment. Pick the floor while things are calm. The other one to watch is a client whose average days late keeps growing, because the forecast uses that number to push their payments out.

We go further on committed vs projected cash, retainage and scenarios in the construction cash flow forecast guide.

3. Job cost

The question: where is each job against budget, cost code by cost code?

How it's built: For each cost code: budget (Procore), committed (Procore commitments), actual in QuickBooks, actual visible in Procore, variance and % used. Card spend that hasn't been coded to a cost code yet shows on its own line, "Uncoded card spend," so the money QuickBooks has and Procore doesn't is never hidden inside another code.

How to read it: Compare the two actual columns first. If QuickBooks actual is higher than Procore actual on a code, the difference is spend the project manager can't see in Procore. Then look at % used against % complete: a code at 90% used on a job that's 50% complete needs a conversation before month-end.

Red flag: a growing gap between QuickBooks actual and Procore actual. The nightly reconciliation compares QuickBooks job cost with Procore direct cost per project, and that gap should trend to $0. If it doesn't, start with the coding queue. The fix for the category-line versus item-line problem behind most of these gaps is in QuickBooks Category details vs Item details.

4. Profitability and portfolio

The question: which jobs, clients and PMs make money, and which don't?

How it's built: Margin is (contract − EAC) ÷ contract. Fade is the points lost against the original estimate. The page also shows gross profit to date (earned minus cost to date), earned versus billed, backlog, months of backlog and a six-month revenue forecast from the backlog burn. Rows roll up by project and by client.

How to read it: In the sample data the portfolio projects a 13.2% margin ($1.92M), $1.12M of gross profit earned to date, $5.88M of backlog and 3.6 months of backlog at $1.62M a month (the last three months of company revenue). Revenue for the next six months comes to $4.45M from backlog and schedules. Sort by client next. Concentration risk shows up here before it shows up anywhere else.

Red flag: margin fade. A job that was bid at 15% and now projects 11% has lost four points, and if the line keeps sliding week to week, the EAC is probably still optimistic. Months of backlog under about three is the other one to watch for a contractor that needs a pipeline to fill the gap.

5. Commitments and buyout

The question: is every budget line bought out, and is anything over-committed?

How it's built: By cost code: budget, committed, uncommitted and buyout variance. Buyout variance is budget minus committed on bought-out subcontract codes: positive is savings, negative is an overrun. There's a second view, the commitment log, listing each subcontract and PO with original value, approved changes, revised value, billed to date, retainage and remaining.

How to read it: The sample portfolio has $11.8M of budget across 132 cost codes, $6.91M committed (58.7%), $4.80M still to buy and 86.4% of subcontract budget bought out. Net buyout is +$67K, which is $152K of savings offset by $85K of overruns. Billed against commitments is $4.51M with $426K of retainage held.

A cropped screenshot of the Commitments and buyout report on sample data. The question line reads: is every budget line bought out, and is anything over-committed? The formula line reads buyout variance equals budget minus committed on bought-out subcontract codes, plus savings, minus overrun. Tiles show budget $11.8M across 132 cost codes, committed $6.91M (58.7% of budget), uncommitted budget $4.80M, buyout net $67K ($152K savings, $85K overruns), 86.4% bought out and $4.51M billed against commitments with $426K retainage held.Commitments and buyout (sample data)

Red flag: a negative buyout variance on a code, or a lot of uncommitted budget on a job that's past 50% complete. The second one often means scope that will be bought late, at a worse price, or self-performed without anyone saying so. A healthy net number can hide one large overrun, so read the overruns column on its own.

6. Vendor spend and uncoded aging

The question: who do we pay, how much, and what is still uncoded?

How it's built: Card spend from Ramp plus subcontract and PO billings from Procore commitments, AP open and retainage payable from QuickBooks. Then top vendors, spend by GL account, spend by cost code, monthly card spend, and the uncoded aging chart: card spend not yet on a Procore cost code, bucketed by days since the transaction.

On the call, Charley put it plainly: many teams want "to identify what's uncoded and what's by age" so they can go and collect on it.

A cropped screenshot of the AP and vendor spend report on sample data. The question line reads: who we pay, how much, and what's coming due. Tiles show card spend $33K from Ramp, commitment billings $4.97M, AP open $729K with $426K retainage payable, and uncoded card spend $14K across 24 items with $5.9K older than 7 days. Below, a chart titled "Uncoded spend aging, the liability hole" and a chart of card spend by month. Buttons for Download CSV and Uncoded items CSV sit at the top right.Uncoded spend aging, the liability hole (sample data)

How to read it: Card spend is small next to commitment billings ($33K versus $4.97M in the sample), and that's normal. The uncoded tile is the one to watch: $14K across 24 items, with $5.9K older than seven days. The "Uncoded items CSV" button gives the controller a list to chase.

Red flag: dollars sitting in the 30+ day uncoded bucket. That cost is in QuickBooks, it's on no Procore cost code, and the longer it sits, the more likely the person who made the purchase has forgotten what it was for.

7. Card spend coding

The question: who still has card charges to code, and how fast do they reach Procore?

How it's built: From the coding pipeline: to code, coded, approved, synced and the median days to code, by cardholder and by GL category, plus unreconciled spend by project and a weekly synced count. Sub-tabs compare QuickBooks with Procore and list exceptions.

How to read it: The sample shows 17 transactions waiting on a cost code, 19 synced to Procore so far and $14K not in Procore across 24 items on 6 projects. Sort the cardholder table by "to code." That list is the follow-up for the week. The approval side of this, where a PM or admin reviews and approves the coded charges, is in the bill and card coding approvals queue.

Red flag: the same cardholders at the top of the list every week, or median days to code creeping past three. That's a habit problem, and a reminder email at the right time usually fixes it faster than a policy memo.

8. Exceptions

The question: what needs a person today?

How it's built: The app checks live for six kinds of exception:

ExceptionRule in the proof of conceptSeverity
QuickBooks ≠ ProcoreAny job where QuickBooks job cost and Procore cost differ by $1 or moreRed over $10K, amber below
Uncoded > 7 daysCard spend not on a cost code more than 7 days after the transactionRed if the oldest is over 30 days
Sync errorsAn expense that failed to sync, or a failed sync run in the last 7 daysRed for expenses, amber for runs
Negative marginA job projecting a lossRed
Overbilled > 10%Over billing above 10% of revised contractRed over 20%, amber over 10%
Red itemsCount of everything redn/a

How to read it: The sample shows six QuickBooks-versus-Procore gaps worth $14K, five uncoded items older than seven days worth $5.9K, one sync error for $205, no negative-margin jobs, no jobs overbilled past 10%, and 12 exceptions in total, one of them red. Every row links to the screen where it gets fixed.

A cropped screenshot of the Exceptions report on sample data. The question line reads: data that needs a person, stale uncoded spend, sync errors, losses, overbilling. Tiles show QBO not equal to Procore 6 ($14K), uncoded over 7 days 5 ($5.9K), sync errors 1 ($205), negative margin 0, overbilled over 10% 0, and red items 1 of 12 exceptions in total.Exceptions: the one list to clear (sample data)

Red flag: anything red that was also red last week. Exceptions are there to be cleared. If an item survives two Mondays, it needs an owner and a date. The thresholds above are a starting point; the data quality side is covered in construction data quality rules.

The Monday read

You don't need to open all eight reports every week. This order works for most owners, and it takes about fifteen minutes:

A checklist of one red flag per report, in reading order. Exceptions: any red item, such as a QuickBooks versus Procore gap over $10K. Card spend coding: charges uncoded after 7 days. Vendor spend: dollars in the 30+ day uncoded bucket. WIP: overbilled by more than 10% of contract or a big underbilling with no pay app due. Cash: the projected low point dips under the floor you set. Profitability: margin fade. Commitments: negative buyout or uncommitted budget past 50% complete. Job cost: QuickBooks actual above Procore actual on a code.One red flag per report, in reading order

  1. Exceptions. Clear or assign every red item.
  2. Card spend coding. Send the "to code" list to the people on it.
  3. WIP. Check the billing position and the biggest under- and overbillings.
  4. Cash. Check the 13-week low point against your floor.
  5. Profitability. Scan for fade.
  6. Commitments. Look at overruns and late buyout.
  7. Job cost and vendor spend only for the jobs the first six pointed at.

The first three usually explain the rest. A cash dip in week nine often traces back to an underbilled job, and an underbilled job often traces back to an EAC nobody refreshed. The project-level version of this, a single grade per job, is in the weighted project scorecard, and the KPI tiles that sit above all of it are in the KPI scorecard starter set.

What makes these reports trustworthy

A report pack is only as good as the inputs. Three things did most of the work for Cattlemen:

  • Card spend reaches Procore. Until card charges carry a Procore cost code, job cost in Procore is short and every report that reads it is short too. The fix and its guardrails are in the job-cost flow fix.
  • The EAC is refreshed monthly. WIP, profitability and margin all hang off one PM number. The month-end review makes the PM submit it and an executive sign off.
  • Every number shows its source and its date. Each page says "as of" and states its formula in a line under the title. When someone asks "where does that come from?", the answer is already on screen.

The project operating system tour shows how the reports connect to approvals, projects, month-end and the company dashboard.

Next step

Print the owner report pack guide: one page with each report, its question and its red flag. Take it to your next Monday meeting and see which questions you can answer today and which ones send someone digging through two systems. The ones that need digging are where to start.

If you want these reports reading your own Procore, QuickBooks and Ramp data, we build this kind of system for contractors. Email charley@buildflows.ai or tell us what you're building.

Frequently asked questions

What reports should a general contractor owner review every week?

Eight cover most of it: the WIP schedule, cash position with a 13-week forecast, job cost by cost code, profitability and portfolio, commitments and buyout, vendor spend with uncoded aging, card spend coding, and an exceptions list. Start with exceptions and card coding, then WIP and cash, and only open job cost for the jobs those point to.

How is percent complete calculated on a WIP schedule?

With the cost-to-cost method, percent complete is cost to date divided by the estimate at completion (EAC). Earned revenue is percent complete times the revised contract. Billed to date minus earned revenue tells you whether the job is overbilled, which is a liability, or underbilled, which is an asset.

Where does WIP data come from with Procore and QuickBooks Online?

Revised contract, budget and commitments usually come from Procore. Cost to date and invoices come from QuickBooks Online. The EAC comes from the PM's cost-to-complete forecast. If card spend never reaches Procore, Procore's cost is short and the gap shows up between the two systems.

How do you build a 13-week cash flow forecast for a contractor?

Start at today's bank balance. Add open receivables on the date you expect to be paid, the due date plus that client's average days late, and scheduled billings. Subtract open payables by due date, a payroll and overhead run rate, and committed subcontractor payments. Read the lowest projected balance against a floor you set in advance.

What is buyout variance?

Buyout variance is the budget for a cost code minus what has been committed on it through subcontracts and purchase orders, measured once the code is bought out. A positive number is savings and a negative number is an overrun. Read overruns on their own, because a positive net total can hide one large loss.

What is uncoded spend aging?

It is card or bill spend that has reached QuickBooks but has not been put on a Procore cost code, grouped by days since the transaction. Procore cannot show that cost on any job until it is coded, so anything older than about seven days should be chased.

What belongs on a construction exceptions report?

Items that need a person: QuickBooks versus Procore job cost gaps, card spend uncoded for more than seven days, failed syncs, jobs projecting a loss, and jobs overbilled by more than 10 percent of contract. Each row should link to the screen where it gets fixed, and anything open two weeks running needs an owner and a date.

Next step

Trying to automate a report like this?

Discuss your current reporting process: what the team does today, which systems are involved, and what you want to change.

Prefer email? charley@buildflows.ai

Keep learning

Custom applications · November 19, 2026

A Contractor's Project Operating System, Screen by Screen: What Each Role Sees and Why

A screen-by-screen tour of the Cattlemen OS proof of concept built for Cattlemen Construction Services in Fort Worth, Texas, on sample data over QuickBooks Online, Procore, Ramp and Microsoft 365. Covers sign-in and Home, My expenses and the approvals queue that gets card spend onto Procore cost codes, the Projects list with convert to won and SharePoint folders, the project page tabs (overview, grade, job cost, expenses, subs, files), the weighted project grade, the month-end cost-to-complete close, the company dashboard, alerts, reports, the platform console with read-only view as, the help center and the AI brain connection through iframe, read-only API and MCP. For each screen: what it shows, which role sees it and why, with sample numbers and timestamps from the walkthrough video.

Reporting & analytics · October 8, 2026

Construction WIP Reporting in Power BI: A Controller's Guide

A practical guide to construction WIP reporting in Power BI: the formulas, where the data comes from in Procore and accounting, the mistakes that make a WIP schedule look right while being wrong, and how to automate it.

Reporting & analytics · October 9, 2026

Construction Cash Flow Forecasting in Power BI: A Practical Guide

A practical guide to forecasting contractor cash in Power BI: start from committed AR and AP placed by due date, keep retainage separate, and layer scenarios with their assumptions written on the page.